Novasun 150L Instruction & Installation Manual - page 12
Copyright © 2014
Ikhwezi Solar (Pty) Ltd, Novatherm CC, Solar Assist (Pty) Ltd
11
10.
System commissioning
10.1
Commissioning direct systems
Make sure that the solar radiation is low during
filling. In strong radiation it is possible for steam
to form in the collector. Keep the collector
covered throughout installation and
commissioning.
Do not turn on the electric backup until the tank
has been filled with water.
Turn on at least one hot water outlet tap and
open the mains water supply to allow the water
to fill the tank and collector, expelling air from the
tank. As soon as water flows freely, without air
sputter, close the tap and allow the cylinder to
pressurise.
Check all piping, joints and fittings for water
leaks.
Check pressure relief valves to ensure correct
operation.
Turn on the electric backup element. Make sure
the tank is completely filled before turning on the
element. Ensure power is available to the backup
element.
Ensure the time clock has been correctly set.
11.
Installation checklist
The following checklist should be observed by the
installer before handing the system over to the
owner/user.
All air bled from taps
System checked for water leaks
Cold and hot water pipes checked for leaks
Roof tiles back in position
Roof flashing watertight
Drain pipes free of obstruction
Pipework insulated
Electrical element, timer switch, isolator
and thermostat, controller and pump
checked
Any protective plastic or packaging stickers
removed from tanks and/or collectors
Owner instructed on use