Ranger 1505-PH Installation Manual - Phase 1
Manual is about: Cargo Rack for Ram ProMaster ( Aluminum )
of
24
For technical support, contact us at 1-800-565-5321
15-U0527 Installation Guide
| REV. A1 | Page
6
1.2.1
Slide carriage bolts on the bottom face of the crossbar.
PHASE 1
– ASSEMBLY
1.2 THIRD CROSSBAR ASSEMBLY
HARDWARE USED
2×
#90-491 Carriage Bolt
5/16" × 1" SS304
HARDWARE USED
2×
#90-491 Carriage Bolt
5/16" × 1" SS304
TIPS:
Use tape to keep the bolts from sliding off.
NOTE:
The track plug must be removed from the underneath of the crossbar, and reinstalled after the
feet have been installed in the final position.
DRIVER SIDE
• Slide 2 pcs. of 1" carriage bolts.
PASSENGER SIDE
• Slide 2 pcs. of 1" carriage bolts.