Sentinel Eliminator Nano Installation Manual

Manual is about: Central Heating Filter

Summary of Eliminator Nano

  • Page 1

    Page 1 eliminator nano installation manual central heating filter version 1 – july 2014 important please retain these instructions for reference during servicing.

  • Page 2

    Page 2 eliminator nano installation manual v1 07/14.

  • Page 3

    Page 3 eliminator nano installation manual v1 07/14 index section page safety considerations 4 general description 5 schematic diagram 6 system design 7 mounting considerations 8 installation procedure 9–11 servicing 12 dosing 13 technical specification 14 guarantee 15 please visit www.Sentinelprote...

  • Page 4

    Page 4 eliminator nano installation manual v1 07/14 safety considerations safety considerations • sentinel eliminator nano® filter is a pressure vessel containing a hot fluid. In the interests of reliable long term operation, it is strongly recommended that the sentinel eliminator nano filter is onl...

  • Page 5

    Page 5 eliminator nano installation manual v1 07/14 general description general description the sentinel eliminator nano central heating filter is designed for the effective removal of all types of debris associated with wet central heating systems. Sophisticated hydrocyclone technology is employed ...

  • Page 6

    Page 6 eliminator nano installation manual v1 07/14 schematic diagram schematic diagram the main elements of the filter are shown below in figure 1. A separate isolation valve is also supplied (see later section ‘installation’ for further details). Directional t piece bleed valve collection bin anti...

  • Page 7

    Page 7 eliminator nano installation manual v1 07/14 system design system design the sentinel eliminator nano filter is suitable for use on sealed and open vented wet central heating systems with 22mm pipework only. Please do not attempt to install on a 28mm system: the cyclones are not optimised for...

  • Page 8

    Page 8 eliminator nano installation manual v1 07/14 mounting considerations mounting considerations before fitting the filter, ensure that adequate clearance is available, including the vertical space required to drain the filter during servicing. The filter can be fitted to either horizontal or ver...

  • Page 9

    Page 9 installation procedure note on isolation valves the filter is supplied with a separate ¼ turn ball valve for isolation purposes. This can be fitted (if desired) during installation. Boilers typically have an integral valve on the return leg, so in instances where full isolation is desired, th...

  • Page 10

    Page 10 eliminator nano installation manual v1 07/14 installation procedure installation procedure (continued) step 1: select a suitable location for the filter and remove a section of pipe 54mm in length. The sentinel eliminator nano should be installed on the return to the boiler. Step 2: unscrew ...

  • Page 11

    Page 11 eliminator nano installation manual v1 07/14 installation procedure step 5: refill and pressurise the system and use the bleed valve to remove any trapped air. Check carefully for any leaks and ensure that the drain valve is fully closed with handle in the horizontal position. Ensure that th...

  • Page 12

    Page 12 eliminator nano installation manual v1 07/14 servicing servicing the sentinel eliminator nano filter requires minimal maintenance other than intermittent flushing to remove any collected debris. This can be done anytime, or at least during the annual boiler service. Care should be taken when...

  • Page 13

    Page 13 eliminator nano installation manual v1 07/14 dosing dosing in instances where full isolation of the filter is achievable (as per figure 3) it is possible to use the filter as a chemical dosing point for sentinel’s rapid dose products following the sequence below: step 1: assemble dosing adap...

  • Page 14

    Page 14 eliminator nano installation manual v1 07/14 technical specification filtration method cyclonic – quad overall dimensions 223mm (h) x 108mm (body diam.) collection capacity 260ml pipe size 22mm flow rate 16–22 l/min max temperature 80°c max pressure 3 bar construction materials glass reinfor...

  • Page 15: Guarantee Registration

    Guarantee registration please complete and return to register your 2 year guarantee. Occupier name address postcode telephone email sentinel performance solutions ltd and its sister companies may wish to send you information on products, services and promotions in the future. If you would like to re...

  • Page 16

    Eliminator nano installation manual v1 07/14 customer services for expert advice, any more information about the sentinel eliminator nano or any other product in the range please contact customer services at: sentinel performance solutions ltd. 7650 daresbury park warrington cheshire wa4 4bs tel +44...