Wacker Neuson EH 6 Operator's Manual - page 28
7 Operation
EH 6, EHB 7
28
Operator's manual
V
e
rsion 00
1
7
Operation
7.1
Prior to starting the machine
After unpacking, the machine is ready for operation.
Checking the machine
f Check the machine and all components for damages.
Checking the mains
f Check if mains or power distribution on the construction site have the correct
operating voltage (see nameplate of the machine or chapter Technical Data).
f Check if mains or power distribution on the constructions site are protected
in accordance with current standards and regulations.
WARNING
Improper handling can result in injury or serious material damage.
f Read and follow all safety instructions of this operator's manual, see chapter
Safety information.
WARNING
Electrical voltage.
Injuries from electrocution.
f Remove the plug from the plug receptacle before all work on the machine.