Xante PlateRunner P24 Supplementary Manual

Summary of PlateRunner P24

  • Page 1

    Corporate headquarters: 2800 dauphin street · mobile, al 36606 · usa usa 800-926-8839 · eu +31 (0) 26.319.3210 · global +1.251.473.6502 · xante.Com ctp site preparation guide • openrip symphony • vm ctp system • platerunner p24 processor introduction installation of your xanté ctp system involves a ...

  • Page 2

    The ctp system and computer can operate from a single, dedicated circuit. In north america and other 120 volt markets, it should be a 120 volt, 15 amp circuit using a nema 5-15 outlet — this is a normal business/household outlet. In europe and other 220-240 volt markets, the circuit should have 10 a...

  • Page 3

    Ancillary parts and supplies your equipment installer will be carrying a ccd dot meter to calibrate the system during installation. However, we strongly recommend that you have a ccd dot meter on hand if you ever need to recalibrate the system. Xanté sells a dot meter, but meters by other leading ma...

  • Page 4

    Please consider the following: • if you do not have a loading dock, please contact xanté to ensure that the crates arrive on a truck which is equipped with a lift-gate. • please ensure that all doors between the delivery point and the installation area are wide enough that the crates can pass throug...

  • Page 5

    Customer equipment delivery checkoff list please check off the following items when they have been completed. All should be complete prior to your equipment shipping. I will require carrier to deliver with lift gate and inside delivery (additional fee for this service). I have measured all doorways ...

  • Page 6

    Customer responsibility checkoff list please check off the following items when they have been completed. All should be complete prior to your scheduled installation date. For users who will put the equipment in a darkroom: i have a darkroom with adequate space for the vm ctp system and p24 processo...