ABS AFP 0831S Installation And Operating Instructions Manual - page 5
InstallationandOperatingInstructions
7
ABS submersible sewage pump AFP 0831S and 0841S
Setupandinstallation
ATTENTION
Allrelevantregulationscoveringsewagepumpinginstallationsand,where
applicable,explosion-proofinstallationsmustbecompliedwith.
c
The cable duct to the control panel should be made gas-tight by filling with foam after the power
supply and control circuit cables have been laid.
m
Particular attention must be paid to the safety regulations covering work in closed areas in
sewage plants as well as good general technical practices .
.1
Installationexampleinconcretesump
Legend
1000-00
1
Sump cover
2
Venting line
3
Sump cover
4
Sleeve for cable
protective duct to
the control panel
5
Chain
6
Inflow line
7
Ball type float switch
8
Submersible pump
9
Concrete sump
10
Pedestal
11
Guide tube
12
Discharge line
13
Non-return valve
14
Gate valve
15 Power cable to motor
Installation example in concrete sump
.2
Dischargeline
The discharge line must be installed in compliance with the relevant regulations.
DIN 1986/100 and EN 12056 applies in particular to the following:
The discharge line should be fitted with a backwash loop (180° bend) located above the backwash level and
should then flow by gravity into the collection line or sewer.
The discharge line should not be connected to a down pipe.
No other inflows or discharge lines should be connected to this discharge line.
ATTENTION
Thedischargelineshouldbeinstalledsothatitisnotaffectedbyfrost.
-
-
-