  • Page 1

    Orion® se gateway transceiver installation & operation manual ori-iom-60 (january 11, 2011 2:30 pm) 62014-xxx rev. 1 important: this manual contains important information. Read and keep for reference..

  • Page 2

    Orion® se gateway transceiver page ii (1-11).

  • Page 3: Contents

    Installation & operation manual contents overview ..................................................................................................................................5 product description .....................................................................................................

  • Page 4

    Orion® se gateway transceiver page iv (1-11).

  • Page 5

    Installation & operation manual overview this manual contains installation and programming instructions for the orion® se gateway transceiver. Proper performance and reliability of the orion® se gateway transceiver depends upon installation in accordance with these instructions. Product description ...

  • Page 6

    Orion® se gateway transceiver installation transceiver main components • twoantennas • onemountingbackplate • oneorionsegatewaytransceiver • mmkbracketorbandingandlockingequipmentforattachingaorionsegatewaytransceivertoapole figure 1: transceiver components tools and materials • philips#2screwdriver...

  • Page 7

    Installation & operation manual installation procedure note: the utility is usually responsible for proper positioning of a the transceiver. For optimum reception and transmission, locate the gateway in line-of-site view of the desired endpoints. 1. Unpack the gateway transceiver. 2. Screw a receivi...

  • Page 8

    Orion® se gateway transceiver 6. Position the transceiver on the pole and place another clamp on the bolts. Figure 3: transceiver positioning and clamp 7. Place another lock washer and nut on each bolt and tighten the bolts. 8. Repeat steps 1 through 7 for attaching the same hardware to the bottom o...

  • Page 9

    Installation & operation manual band-it® mini-brack-it mounting this mounting equipment is sized to mount the gateway transceiver on a 2½ inch to 24 inch diameter pole. 1. To mount the orion se gateway transceiver on a pole, gather the banding and locking equipment, badger meter part number: 66042-0...

  • Page 10

    Orion® se gateway transceiver figure 7: close up of right side band-it connection assembly instructions for m12 connector (power source) note: use only approved badger meter cable, part numbers: 66233-015 (100 ft) or 66233-017 (300 ft) for this assembly. Connector part names figure 8: connector part...

  • Page 11

    Installation & operation manual 2. Strip the cable outer jacket to a length of 1.1 inches. Maximum. Figure 11: stripped cable wires 3. Shorten the foil shield flush with the outer jacket. 4. Strip the ends of the six (6) wires to a length of 0.16 inch. Twist the conductors on each wire. 5. Shorten t...

  • Page 12

    Orion® se gateway transceiver electrical / network installations gprs / wi-fi installation figure 12: gprs / wi-fi connections install a nema (4x if outdoors) enclosure according to state and local electrical codes, installed to be accessible by authorized personnel from ground level. Minimum enclos...

  • Page 13

    Installation & operation manual lan installation figure 13: lan connections with separate ac power figure 14: lan connections (poe) (1-11) page 13.

  • Page 14

    Orion® se gateway transceiver install a nema (4x if outdoors) enclosure according to state and local electrical codes, installed so as to be accessible by authorized personnel from ground level. Minimum enclosure size: 12” x 10” x 6” your nema enclosure should contain a hole large enough to pass the...

  • Page 15

    Installation & operation manual battery installation/replacement in the event a battery replacement is required, please complete the installation steps as detailed below. 1. Remove enclosure cover by unscrewing four, corner cover screws and discard the cover (the cover will not be used again). Cover...

  • Page 16

    Orion® se gateway transceiver 4. Place new battery in unit with the battery label (“this side out”) visible and upright (see "figure 17: battery remov- al" on page 15). 5. Carefully install the battery connector onto the circuit board. Connector needs to be inserted only far enough so that the conne...

  • Page 17

    Installation & operation manual software configuration the orion se gateway transceiver software configuration settings were preset prior to delivery. The following instructions supply a basic overview for changing the network and gateway settings. Badger meter suggests contacting customer service, ...

  • Page 18

    Orion® se gateway transceiver (tcpconnection) 10. Click on the gateway id number when it appears and then click the select button. For the serial connection: 11. View the gateway select screen: note: if the gateway select screen indicates an error due to an unsuccessful gateway connection, click the...

  • Page 19

    Installation & operation manual 12. Click the select button to open the gateway configuration screen. (1-11) page 19.

  • Page 20

    13. View the identification menu: 14. Click on the network icon on the left side of the screen. Due to continuous research, product improvements and enhancements, badger meter reserves the right to change product or system specifications without notice, except to the extent an outstanding contractua...