4. Planning before installation
The equipment must be installed in upright position. The equipment requires space to front and
back to enable cooling airflow. Service and maintenance require 500 mm clearance on right
hand side. All cooling air enters at front and exits at unit rear. The required min. clearance from
unit rear to an obstruction is 250 mm. Because the service and user access is in the front there
should be reserved enough space (min 600 mm).
It is required to arrange ventilation of the UPS room. Sufficient amount of air cooling is needed
to keep the max. room temperature rise at desired level:
•
Temperature rise of max. +5
°
C requires the airflow of 600 m
3
per 1 kW of losses.
•
Temperature rise of max. +10
°
C requires the airflow of 300 m
3
per 1 kW of losses.
An ambient temperature of 15 to 25 Celsius degrees is recommended to achieve a long life of
the UPS and batteries. The cooling air entering the UPS must not exceed +40 °C. Avoid high
ambient temperature, moisture and humidity.
The floor material should be non-flammable and strong enough to support the heavy load. The
UPS has (4) leveling feet that should be used when finalising the installation. The diameter of a
single leveling foot is 29 mm.
Equipment
Weight
Point
Distributed
Note
20-30 / 40 kVA
20-30 / 40 kVA
20-30 / 40 kVA
UPS w/o BAT
200 / 217 kg
7.57 / 8.21 kg/cm
2
531 / 576 kg/m
2
No Batteries installed
UPS+1 BAT
300 / 317 kg
11.35 / 12 kg/cm
2
797 / 842 kg/m
2
1 Battery string installed
UPS+2 BAT
400 / 417 kg
15.14 / 15.78 kg/m
2
1063 / 1108 kg/m
2
2 Battery strings installed
UPS+3 BAT
500 / 517 kg
18.92 / 19.56 kg/cm
2
1328 / 1373 kg/m
2
3 Battery strings installed
UPS+4 BAT
600 / 617 kg
22.71 / 23.36 kg/cm
2
1594 / 1639 kg/m
2
4 Battery strings installed
EXT BAT 0
150 kg
5.67 kg/cm
2
401 kg/m
2
No Batteries installed
EXT BAT 1
510 kg
19.29 kg/cm
2
1362 kg/m
2
1 Battery string installed
EXT BAT 2
870 kg
32.90 kg/cm
2
2323 kg/m
2
2 Battery strings installed
Table 1
The floor surface must tolerate loading.