8.
Now, please follow the steps that are shown at the table below.
9.
ALWAYS DEFINE A COOL DOWN SEGMENT TO ROOM TEMPERATURE AT THE END OF THE
PROGRAM. OTHERWISE, AFTER THE PROGRAM HAS COME TO AN END THE FURNACE
TEMPERATURE WILL STABILIZE AT THE LAST SEGMENTS TEMPERATURE VALUE UNTIL
THE POWER IS TURNED OFF.
Prompt
Function
Segment
Value
STRSEG
•
Starting Segment
-
1
•
The segment number which the program will begin.
•
You may adjust the values with respect to functions
mentioned in this table by pressing “
▲
" or “
▼
" button.
•
Always , press "FUNCTION" button to confirm the
value and to pass to next step.
ENDSEG
•
End Segment
-
max.12
•
The segment number which the programe will end.
RP UNIT
•
Engineering Unit for Ramp.
-
TIME
•
Defines heating up or cooling down speed.
•
Can be chosen as TIME (Hr:Min)
EU-H (°C/hr)
EU-M (°C/min)
PG END
•
Controller Status
-
LAST SP
•
Do not change default value
STATE
•
Controller State at the end
-
HOLD
•
Do not change default value
TO BEGIN
•
Reset SP Program
-
DIS
•
Do not change default value
PVSTRT
•
Program Starts at PV Value
-
ENB
•
Enable the function by pressing “
▲
" or “
▼
" button.
RECYCL
•
Number of Recycles
-
0
•
Defines how many times will the program will repeat.
SOKDEV
•
Deviation Value
-
0
•
Do not change default value
SG1RP
•
Ramp Time
1
1 hr
•
Defines the heat up time between two set points (SP)
•
Units are:
1. Hr:Min if TIME option is adjusted in the RPUNIT menu.
(TIME in this example)