Logano G334X Installation And Service Instructions Manual - page 9
5
Tank installation
Logano G334X – 6 720 811 237 (2014/05)
9
(155 mm) is also required for the flue pipe and 30 inches (762 mm)
clearance to the ceiling.
Fig. 5
Wall clearances in the boiler room
[1]
Closed door
[2]
Open door
4.3
Leveling the boiler
The boiler must be leveled horizontally and vertically to prevent air
pockets forming inside.
▶ Level the boiler vertically and horizontally, inserting metal wedges or
shims underneath as required.
Fig. 6
Leveling the boiler (example)
5
Tank installation
This section details how to install your boiler correctly. This involves the
following steps:
• Flue connector
• Heating circuit connection
• Electrical connections
• Connecting the fuel supply
5.1
Preparing for installation
▶ Unpack all cartons and boxes.
▶ Using the included packing list, check to be sure that you have all the
included parts.
Route the gas connection towards the left
If the gas connection needs to be on the left:
▶ Loosen the unions on the gas supply pipe completely.
▶ Reattach and seal the gas supply pipe after rotating it 180°.
▶ Carry out leak test.
5.2
Installing the flue gas collector or the collection
manifold
▶ Fasten the flue gas collector to the draft diverter with the eight
retaining screws.
Fig. 7
Installing the flue gas collector Logano G334 X
[1]
Retaining screws on draft diverter
NOTICE: Risk of system damage due to contamination!
▶ If the boiler is not to be installed immediately, protect
the connections from entry of dirt.
1
2
6 720 806 028-05.1T
6 720 810 547-32.1T
Every boiler is carefully inspected and tested before it
leaves the factory. However, if you discover any damage
or missing parts, please inform the supplier
immediately. Before disposing of packing material,
make sure that no parts are still in it.
The gas supply pipe is designed for a gas connection on
the right side.
6 720 810 547-06.1T
1
1