LEGEND (see fig. 1)
1. ON / OFF POWER BUTTON
2. HEATING TEMPERATURE ADJUSTMENT KNOB
3. DOMESTIC HOT WATER TEMPERATURE
ADJUSTMENT KNOB
4. OUTSIDE TEMPERATURE DISPLAY PAD (ONLY WITH
OPTIONAL OUTSIDE TEMPERATURE SENSOR
FITTED)
5. CHIMNEY-SWEEPER SELECTION PAD/PARAMETER
SETTING SERVICE PAD
6. MODE SELECTION PAD (SUMMER ONLY / WINTER
ONLY / SUMMER AND WINTER)
7. MAIN EXTERNAL TERMINAL BLOCK (POWER
SUPPLY )
8. DOMESTIC HOT WATER MODE (STABLE LIGHT)
DOMESTIC HOT WATER OPERATION (FLASHING
LIGHT)
9. HEATING MODE (STABLE LIGHT)
HEATING OPERATION (FLASHING LIGHT)
Fig. 1
10. GENERAL LOCK-OUT WITH FLASHING ERROR CODE ON DISPLAY (14)
11. WATER PRESSURE LEVEL 1.5 BAR INDICATOR
12. WATER PRESSURE LEVEL 1 BAR INDICATOR
13. WATER DEFICIENCY INDICATOR
14. TEMPERATURE AND ERROR CODES DISPLAY
ERROR CODES:
1. IONISATION LOCK-OUT
2. HIGH LIMIT THERMOSTAT LOCK-OUT
3. FLUE SAFETY THERMOSTAT LOCK-OUT (Not applicable)
4. WATER PRESSURE SWITCH LOCK-OUT
5. HEATING SENSOR FAILURE
6. DOMESTIC HOT WATER SENSOR FAILURE
12. STORAGE TANK WATER SENSOR FAILURE
14. AIR PRESSURE SWITCH / WATER PRESSURE SWITCH LOCK-OUT
22. REQUEST OF PARAMETERS RE-SETTING
STARTING UP THE BOILER
After connecting up the water supply, before starting up the boiler, carry out the following procedures:
Preliminary procedure
• Do as follows:
• make sure the power supply for the boiler is the same as that stated on the plate (230V - 50Hz) and that the live, neutral and earth
connections have been properly connected;
• make sure the type of gas being supplied is the same as the type for which the boiler has been tested and approved (see plate data);
• make sure the unit is properly earthed;
• make sure there are no flammable liquids or materials in the immediate vicinity of the boiler;
• make sure that any shut-off valves in the heating circuit are open;
• open the gas cock and check the gas seals, making sure the counter shows no sign of leaks; in any case, double check by using a soapy
solution and eliminate all eventual leaks. The checking procedure for the gas burner attachment is carried out with the boiler working;
• make sure the electrical mains switch is OFF;
• remove the front cover by pulling it forwards;
• undo the side screws and rotate the panel downwards
Filling the system
After making sure the gas cock is closed, fill the heating system as follows;
• fill the system until a pressure of 1.5 bar has been reached (light no. 11 ON; see fig. 1) and then close the tap on the filling loop;
• make sure the cap on the auto air vent valve is slightly loose to allow air to escape from the system;
• undo the cap on the circulation pump to eliminate any eventual air locks; it is a good idea to purge all radiators of air at this point too;
• before starting up the boiler the water pressure must be checked again; if this is seen to be below 0.5 bar, bring it back up to 1.5 bar (light
no. 11 ON; see fig. 1) and close the tap on the filling loop.
• set ON/OFF switch in ON position (fig.1), after a few seconds the pump will come into operation;
• once the boiler is working, if any noises are heard in the system, repeat the above air purging procedures until there is no air left in the
system;
• check there are no obstructions in the exhaust duct;
DOMESTIC HOT WATER WITH STORAGE CYLINDER – TA05A027.A0504
13