BAK PLANON Operating Instructions Manual - page 6
BAK Thermoplastic Welding Technology Ltd 6
According to the geomembrane liner or film and climatic influence, adjust the welding speed
using the potentiometer.
Welding pressure:
The self-weight of the machine transfers the welding pressure directly onto the pressure roller.
TOOL DESCRIPTION
1
Main switch
ON
/
OFF
2
Drive manual
ON
(only when the button is pressed)
3
Adjustment air flow
4
Adjustment welding speed
5
Heating
ON
/
OFF
6
Adjustment welding temperature
7
Hot air tool
8
Guide roller
9
Carry handle
10
Weight
11
Lifting device
12
Pressure roller
WELDING
Operating condition:
• Maintain the maximal allowed impedance
Z
max
= 0.301Ω + j 0,188Ω. Consult your
local electricity board if necessary.
• Check adjustment of the nozzle.
• The mains supply must conform to ICE 60364 standard as well as to the national
standards.
• Connect the machine to the mains. The voltage rating stated on the tool should
correspond to the mains voltage.
• When using extension cords the minimum diameter of the cable must be observed.
Cord length up to 25 m, cord diameter 3x2.5 mm².
Welding procedure:
• Adjust the welding parameters.
• The welding temperature must be reached.
• Position the welding machine on the overlapped geomembrane liner or film.
• Align the guide roller to the overlap.
• Lower the hot air tool and slide the nozzle between the overlapped geomembrane liner
or film.
1
4
3
6
7
8
9
10
11
12
5