5 Commissioning (functional checks)
For a pre-delivery check, carry out the following tests:
5.1.1 Check function and ignition pilot light and main burner.
• Check whether the pilot light is not covered by chips, a log or pebbles.
• Ignite the hearth as is described in the user’s manual.
• Check whether the pilot light is situated properly above the main burner.
• Check the gas pipes at all connections and gas nipples for gas leakage with a gas
leak detector spray or a gas leak detector.
• Check the ignition of the main burner on full output and low output. (ignition
should be flawless and easy).
5.1.2 Check the flue pipe system
• Let the hearth burn on full output.
• Check the flame image. There should be no flames against the glass and an even
distribution of the flames. If this is not correct, check the positioning of the wood
in the grate and the quantity of chips on the burner.
• After 20 minutes, check if the flames burn a clear yellow. In case of blue flames,
turn the fire off. Check:
• The connections of the pipes (no leakage).
• The mounting of the outlet. In case of wall transit, the proper side up.
In case of roof transit, the proper place (see also chapter 3).
• Whether the maximum length of the flue pipe has not been exceeded.
• Whether the correct baffle has been mounted.