Figure 3-2. Shielded Cable Preparation
1. At the end of the shielded cable, strip back a 2.5" maximum length of the jacket to expose the
braid. Remove this exposed braid. Carefully score the jacket 1/4" to 5/16" from the end and
remove the jacket to leave the braid exposed.
NOTE
Solder sleeves with pre-installed shield drains may be used instead of separate shield
terminators and individual wires. Using solder sleeves with pre-installed lead effectively
takes the place of step 7.
2. Connect a 22 AWG wire to the exposed shield of the prepared cable assembly. AC 43.13 may be a
helpful reference for termination techniques.
NOTE
Solder Sleeves with pre-installed lead: A preferred solder sleeve is the Raychem S02
Series with the thermochromic temperature indicator. These solder sleeves come with a
pre-installed lead. For detailed instructions on product use, refer to Raychem installation
procedure.
3. Slide a shield terminator onto the prepared cable assembly and connect the wire to the shield using
a heat gun approved for use with solder sleeves. The chosen size of solder sleeve must
accommodate both the number of conductors present in the cable and the wire to be attached.
4. Repeat steps 6 through 8 as needed for the remaining shielded cables.