Before starting:
The final thickness of all mortared joints must be 10 mm, both to walls and be-
tween the parts. Check at every stage that the parts have been installed level. It is a good idea to
use the dimensions on page 12 to check your construction height. For putting the stove together, we
recommend you use a B mortar. For rendering the stove, we recommend you use a C mortar.
INSTALLATION INSTRUCTIONS
Before starting on the installation of the stove, the following steps need to be fully completed:
The chimney:
Alternative 1 An existing chimney prepared for rear connection.
Alternative 2 A newly installed chimney prepared for rear connection.
Alternative 3 Preparation for a new top connection chimney.
Erection of fire wall, where applicable.
Outdoor air supply
(if so required)
Hearth floor plate
(unless a floor plate or floor stone is to be installed afterwards)
1. Assemble element no. 1 in mortar. Fill the crack in
the wall with mortar.
NOTE! Check that the elements are level.
2. Install the fan box and the enclosed electricity pipe
as shown in the illustration. If a fan has been ordered
(Accessory), run the cable to the outside of the stove.
The electrical connection must be done by a certified
electrician.
NOTE! If you do not install a fan box now, it cannot be
installed at a later date.
3. Assemble element no 10 in mortar with 10 mm mor-
tared joint between both the base and the floor.
4. Place mortar on element 1 and element 10 and
install element 2.