1.3. Anchoring Bases
1.
FOR ONE BASE ONLY:
a. Mark the center hole and the two corner holes (Use a Marker, a Pencil or Chalk).
b. See floor anchor installation instructions on previous page.
c. Drill and install
ONLY
the center hole anchor using the base plate as a guide.
d. Bolt the base down at the center hole using the bolts and washers provided.
e. Drill corner holes using the base plate as a guide.
f. Install the floor anchors in the corner holes and bolt down corners of the base.
2. Check installed base to make sure it is sitting flat on the concrete.
3. We will now use the rail placed into the carriers on both sides to determine the location of the
second base (See step 5 on page 4 on how to remove hold down brackets if needed).
4. Set the bar to the lowest position on the uprights. Pay attention to the following:
•
Make sure the bar carrier locks into the hole on the adjusting tubes thanks to the pin of the
Gravity Snaplock.
•
Make sure both sides of the bar are in the same hole positions.
•
Leave T-Handles on the base and on the rail carrier loose.
5. Align the uprights so that they are square to each other. Measure outside corner to outside
corner, as well as diagonal corner to corner. Measurements should be equal (Refer to the
drawing below).
Adjusting tube should have play in base tube. Leave T-Handles loose.
6. Check location of the second base by moving the rail in and out of the carrier. Move the base
until the rail goes in and out of rail carrier easily.
7. Make sure second base is sitting flat on the concrete. Install the second base using the
instructions outlined in Step 1.
Approximately 139-3/4”
Diagonal:
Approximately 142-3/8”