Sussman SSB 12-18 Installation, Operation And Maintenance Manual

Manual is about: SSB series

Summary of SSB 12-18

  • Page 1

    Table of contents dimensional information and component identification . . . . . . . . . . . . . . . . . 2 dimensional & clearing specifications . . . . . . . . . 3 wiring diagrams . . . . . . . . . . . . . . . . . . . . . . . . . 4-5 installation piping, wiring . . . . . . . . . . . . . . . . . . ....

  • Page 2

    Installation, operation & maintenance manual dimensional information & component identification 2 _______________________________________ water steam model h w* l inlet outlet _______________________________________ ssb 12–18 37" 22" 32" 1/2”npt 1/2”npt ______________________________________________...

  • Page 3

    Installation, operation & maintenance manual 3 dimensional & clearance specifications steam outlet operating pressure control high limit pressure control pressure gauge safety valve liquid level control water feed inlet f e l d a b e r front left drain valve on/off switch gauge glass assembly height...

  • Page 4

    Installation, operation & maintenance manual wiring diagram control circuit 4 field wiring factory wiring 120v 1ph input control terminal block 7-day 24 hr timer es81600 automatic blowdown system time delay relay pilot light open close motorized blowdown valve solenoid valve pump motor c1 c2 contact...

  • Page 5

    Installation, operation & maintenance manual wiring diagram power circuit h1 h3 h5 h7 fb1 fb2 fb3 fb4 field wiring factory wiring pilot light 480v 120v notes: 1. Power terminal block only on boilers with two or more contactors 2. Power fuses only on boilers rated 120 amperes and larger. 3. See parts...

  • Page 6

    All electrical wiring must be performed by a qual- ified electrician in accordance with national and local electrical codes. Assure that the power voltage and phase being supplied to the boiler matches the power voltage and phase of the boiler. Connecting incorrect power supply can damage boiler com...

  • Page 7

    Installation, operation & maintenance manual 7 pressure controls, operation and testing note: all boilers are provided with one high limit pressure control and at least one operating pressure control. 1. The high limit pressure control is equipped with a manual reset feature. There is no subtractive...

  • Page 8

    Operation with main disconnect “off” tighten all electrical connections before energizing boiler to prevent arcing, carbonizing of contact and/or over- heating 1. Set the desired operating pressure and differential pressure on the operating pressure control. 2. Set the high limit pressure control. (...

  • Page 9

    Installation, operation & maintenance manual 9 digital timer - operation instructions to set time & day of clock 1. Press menu 2. 24h am or pm blinking, press + or – to select, press ok 3. Hour ( 12 :00) blinking, press + or – to select, press ok 4. Minute (12: 00 ) blinking, press + or – to select,...

  • Page 10

    Installation, operation & maintenance manual 10 24-hour and 7-day time switches programming f or electric steam boilers equipped with automatic blowdown systems es 81600, refer to the following instruc- tions for time clock operation and settings. Timer settings for blowdown operation are at the dis...

  • Page 11

    Installation, operation & maintenance manual 11 maintenance hazard of electric shock. Disconnect all electrical power before working on boiler. S ussman electric steam boilers are designed for years of trou- ble-free performance. To establish a good preventative mainte- nance program, we suggest tha...

  • Page 12

    Optional equipment installation, operation & maintenance manual standard equipment 12 auxiliary low water cut off • for model ssb boilers ssb81017mr (with manual reset). Senses water level electronically using a resistance probe. When a low water condition is detected, the contactor control voltage ...

  • Page 13

    Installation, operation & maintenance manual optional equipment (cont.) 13 blowdown separators (see page 14) • for models ssb12-48 pn bdt-asme36 • for models ssb60-180 pn bdt-asme42 a separator accepts the flash steam and effluent from the boiler blowdown and reduces the tempera- ture and pressure t...

  • Page 14

    Installation, operation & maintenance manual 14 blowdown separator tanks- specifications and data models bdt-asme 36, 42 d a h g the sussman separator design incorporates a water seal at the outlet which permits the operator to introduce cold water from the bottom to mix with the hot water and boile...

  • Page 15

    Installation, operation & maintenance manual specifications steam gauge pressure/ temperature chart 15 __________________________________________ boiler bhp lbs/hr 3-ph model no. Kw rating steam** volts*** amps __________________________________________ 208 34 ssb-12* 12 1.22 36.2 240 29 480 15 ____...

  • Page 16

    Installation, operation & maintenance manual sizing 16 use the following table to determine kw boiler rating when steam load and feedwater temperatures are known. _________________________________________________________ feed water 0 2 10 15 25 40 50 75 100 ( f˚) ____________________________________...

  • Page 17

    Important note: read all warnings and instruc- tions before performing installation or maintenance. Safety glasses and gloves should be worn at all times when working with or examining water gauge glass and connections. Pressure in gener- ator to be at zero before proceeding. Improper instal- lation...

  • Page 18

    Installation, operation & maintenance manual gauge glass installation - use and care 18 do nots • do not use glass if it contains any scratches, chips, or any other visible signs of damage. • do not reuse any tubular glass or glass packings. • do not subject gauge glass to bending or torsional stres...

  • Page 19

    Installation, operation & maintenance manual element replacement 19 read instructions completely before starting work before installing your new elements be sure the low water cut-off and aux. Low water cutoff (if supplied) is operating properly. The float chamber and lower equalizer column of the l...

  • Page 20

    A division of sussman-automatic corporation 43-20 34th street, long island city, ny 11101 • 718-937-4500 1-800-238-3535 • fax: 718-937-4676 • email: seb@sussmancorp.Com www.Sussmanboilers.Com pur 101137ssb 3/13 m a d e i n u s a.