Ansal BlueStar Installation Manual - Indoor Unit Installation
NOTE:
Remark per EMC Directive 89/336/EEC
For to prevent flicker impressions during the start of the compressor (technical process),
following installation conditions apply.
1. The power connection for the air conditioner has to be done at the main power distribution.
The distribution has to be of a low impedance, normally the required impedance reaches
a 32A fusing point.
at
2. No other equipment has to be connected with this power line.
3. For detailed installation acceptance, please refer to your contract with the power supplier
restrictions do apply for products like washing machines, air conditioners or electrical
if
ovens.
4. For power details of the air conditioner, refer to the rating plate of the product.
5. For any question contact your local dealer.
3
INDOOR UNIT INSTALLATION
Carry out the pipe and line operation in the ceiling after finishing the installation of the main
body. While choosing where to start the operation, determine the direction of the pipes to
be drawn out. Especially in case there is a ceiling, position the refrigerant pipes, drain pipes,
indoor & outdoor lines to the connection places before hanging up the machine.
The installation of hanging screw bolts.
Wooden construction
Install the main body
Installing f10 hanging screw bolts. (4 bolts)
Please refer to the following figure for the distance measurement between the screw bolts.
Please install with f10 hanging screw bolts.
The handling to the ceiling varies from the constructions, consult the construction personn-
els for the specific procedures.
1. The
size
of
the ceiling to
be handled ... ... do keep the ceiling flat. Consolidate the roof
beam for possible vibration.
2. Cut off the roof beam.
3. Strengthen the place cut off, and consolidate the roof beam.
Put the square timber traversely over
the
roof beam, then install the hanging screw
bolts. (Refer to Chart 1)
Chart 1
Timber over the beam
Roof beam
Hanging screw bolts
Ceiling
New concrete bricks
Blade shape
insertion
Slide insertion
Chart 2
Inlaying or embedding the screw bolts.
(Refer to Chart 2)