Goldstein E201 Installation procedures manual - Commissioning Check List
2. COMMISSIONING
COMMISSIONING APPLIANCE – DETAILS, TESTING, CHECKING PRESSURE
ETC.
COMMISSIONING CHECK LIST
1.
CHECK FOR DAMAGE AND MISSING PARTS ON BACK OF WARRANTY
CARD.
2.
REMOVE ALL PLASTIC COATING FROM S/STEEL PANELS.
3.
MAKE SURE ALL PARTS ARE IN THEIR CORRECT POSITION E.G.
TRAYS CONTROL KNOBS.
4.
MAKE SURE ALL GAS CONNECTIONS ARE CORRECT AND TIGHT.
5.
LEVEL OFF UNIT LEFT TO RIGHT AND FRONT TO BACK.
6.
TURN ON ELECTRICITY.
7.
TURN ON ONE AT A TIME TO MAKE SURE ALL IS WORKING E.G.
BURNER, RADIANT, GRIDDLE AND OVEN.
8. SHOW
CUSTOMER
A)
HOW TO WORK EQUIPMENT
B)
HOW TO CLEAN
C)
HOW TO PULL IT APART E.G. TRAYS.
D)
ALSO WHAT NOT TO DO, E.G. GREASE AND OIL IN CONTROLS.
9.
CHECK TO MAKE SURE MANUALS AND WARRANTY CARD IS THERE.
ALSO GO THROUGH MANUAL WITH CUSTOMER
NOTE:
WASH HOSES SHOULD NEVER BE USED ON THE APPLIANCE.
USE OF HOSES WILL VOID WARRANTY.
IM010B1/p4