5. CONSIDERATION FOR LIFT PLACEMENT
•
Before beginning the installation, check the dimensions of the lift against the available space above the
ceiling. Be sure to include the projector lens and any accessories which may add to the overall
dimensions
•
Preliminary measurements should also be made to layout the orientation of the projector and lift to the
screen. Consider if the lens is offset from the center of the projector and thus the center of the Lift.
6. LIFT SUPPORTING STRUCTURE
The SVS 12HSE Lift should be mounted
from six 1/2” rods. The mounting hole
locations are marked with a
Figure 3. The thread rods must be
supported by a rigid structure. If the
threaded rods exceed more than 2-feet
(0.6 M) from the support structure to the
lift's top mounting holes cross bracing
should be installed between the support
rods. Figure 4 shows the cross bracing
and the correct height for mounting the
lift above the false ceiling.
Note: SVS 12HSE Lift Dimensions
may vary with projectors. Please
verify the Lift dimensions on the Lift
Dimension drawing included in the
Lift Installation package.
SVS 12HSE Lift Installation Instructions
Page 6 of 16
Figure 2. SVS 12HSE Front & Side Views
Figure 3. SVS 12HSE Top View