Fadini COMBI 740 Instruction Manual - page 6
6
PIC. 8
PIC. 10
PIC. 9
SB
SB
PIC. 11
®
Once the concrete has set, put the combined unit in the enclosure and screw it down by means of the two long bolts supplied with the
equipment, see picture No. 10.
Attention: follow the wiring and connecting procedure on page 9 and picture 18. Allow the operators to run full movement 3 times before
hanging the gates. Weld the fixing plate to the gate, either the non-locking type or locking type, which can be released for emergency.
Picture 8 or 9.
WELDING
LOCKING SHOE IN
RELEASED POSITION
OR: NON LOCKING GATE
FIXING PLATE WITH
SHAFT FITTING COLLAR
BOX SPANNER
LONG BOLTS COMBI 740
SB
RELEASE
Once satisfied that everything has been done as described so far,
make sure that the two units are mounted on the correct side of the
gate, view from inside the property: the unit marked “D” on the right-
hand side and “S” on the left-hand side. The COMBIs are designed
as handed operators, the correct position is essential to the
performance of the system. Picture 11.
L
HAND RELEASE
HYDRAULIC RELEASE
FOR THE FIRST OPERATIONS
“S”
JACK/PUMP
LEFT-HAND SIDE
R
HAND RELEASE
HYDRAULIC RELEASE
FOR THE FIRST OPERATIONS
“D”
JACK/PUMP
RIGHT-HAND SIDE
GATE STOP
VIEW FROM INSIDE THE PROPERTY