Figure 7.
DETAIL F
F
Panel hanger brackets
2. Install panels, starting at the bottom. The panels must be placed against the studs and moved downward so
that the panel hangers engage properly. Make sure panel seams are aligned with one another and outside
perimeter panel edges are flush before proceeding to next step.
Figure 6.
Drywall down
to indexing
point
1/4" filler required to cover base (provided by others).
This material could be drywall, plywood, masonite or
other material specified by contractor.
PANEL & TRIM INSTALLATION
1. Drywall to the side edges of the Form® headwall framing (drywall should cover headwall mounting bracket
shown in Unit Installation, Step 2) above the headwall. Drywall above the headwall should terminate at the
upper drywall indexing location (i.e. bracket with leg bent outward indicating termination point of drywall).