Appendix A: Commissioning Handover Certificate
POD Point EV charging equipment will provide basic functionality on first installation, however each point must be
registered and commissioned onto the POD Point network to enable full functionality and remote support. The data
below should be completed for each installation and returned to installations@pod-point.com. Where a latitude and
longitiude are not available, please supply a detailed description and photograph of the charging point location.
This certificate may be completed by hand and scanned to email, or please contact the above email address to re-
quest a soft copy of the certificate in Word.
Please complete Sections 1, 2, 3 and 4. POD Point will complete Sections 5 and 6, to finalise activation. The completed
certificate may be returned for the post owner, on request.
1. POD Location Details to be Completed
POD Location name
POD Location address
Postcode
Latitude
Longitude
2. POD Owner Details to be Completed
Owner / Customer
Owner address
Owner postcode
Postcode
Contact name
Contact number
3. Commissioning Details to be Completed
Date
PPID
Source of electricity (ref no/description)
Confirm power switched on
Confirm functional test complete
Communications test complete: phone POD Point on 020
7247 4114
Electrical Safety Test Certificate No. BS7671 (attach copy)
Feeder pillar Key number
Key holder
Orange signal (stength dBm)
Version 2.2 2012 POD Point Limited w: www.pod-point.com t: 0207 247 4114 e: enquiries@pod-point.com Pg. 10