POD Point PP_2111 Installation Manual - Section 3 : Electrical Work
Each POD Point ideally needs a 240V single phase connection capable of continuously supplying >64 A. This will allow
for easy upgrading for faster charging options in the future. Where such a supply is not possible, PP_2111 will accept
a 45A supply, or POD Point can configure a power management feature to reduce total load to 32A if required (please
contact POD Point to discuss this). Each POD Point also needs a separate earth (not connected to neutral) usually
supplied by an Earth spike or mat (TT system), which is fed into the POD Point via a separate conductor. The earth
should have a maximum resistance of 20 ohms.
There are typically two types of cable installation:
t
Dedicated supply direct onto main, grid.
t
Extension to existing supply.
Connection
2 standard BN25 SWA cable glands are provided to allow cable termination at the charging point. Models fitted with a
4-way switch disconnector may be supplied from either a 240VAC single phase or a 415VAC 3-phase supply.
Units are supplied with a jumper between L1 and L2 on the supply side to allow connection to a single phase supply.
This should be removed if installing a 3-phase supply. If both sockets are to be fed from the same phase, then the
power conductors on the load side should be moved from L1 and L2 to a common phase as required.
The incoming terminals will accomodate rigid conductors up to 55mm
2
or flexible conductors up to 35mm
2
All electrical installations must be carried out by a qualified electrician an be in compliance with BS 7671.
Section 3 : Electrical Work
Version 2.2 2012 POD Point Limited w: www.pod-point.com t: 0207 247 4114 e: enquiries@pod-point.com Pg. 6