Safety glasses and gloves should be worn at all times when working with
or examining water gauge glass and connections.
Pressure in generator to be at zero before proceeding.
Improper installation or maintenance of gauge glass and connections can cause
immediate or delayed breakage resulting in bodily injury and/or property damage.
Sussman Boilers
Installation, Operation & Maintenance Manual
Gauge Glass Installation
20
IMPORTANT NOTE:
Read all warnings and instructions before
performing installation or maintenance. Safety glasses and gloves
should be worn at all times when working with or examining water
gauge glass and connections. Pressure in generator to be at zero
before proceeding. Improper installation or maintenance of gauge
glass and connections can cause immediate or delayed breakage
resulting in bodily injury and/or property damage.
1.
Apply Teflon tape or pipe dope to pipe threads. Install top gauge
fitting (fitting without a drain valve) into the uppermost tap-
ping.Wrench tighten the fitting until it is snug and the glass outlet
is pointing at five o'clock (about 1/8 turn from its final downward
vertical position).
2.
Install the bottom gauge fitting (the fitting with a drain valve)
until it is snug and the glass outlet is pointing directly
upward.Verify top and bottom fittings are threaded into the tap-
pings the same number of turns (distance A= distance B).
3.
Remove glass packing nut, friction washer (or packing gland,
depending upon the model), and glass packing from the fittings,
and place them, in the same order, on to both ends of the gauge
glass. Push both packings about an inch up the gauge glass.
4.
Gently insert one end of the glass into the top gauge fitting.
Keeping the glass inside the top fitting, gently rotate the top
gauge fitting clockwise until vertically aligned with the bottom
gauge, then insert glass into bottom fitting until glass bottoms out
on the shoulder inside the bottom fitting.
5.
Carefully raise glass about 1/16" and slide lower glass packing
down until the glass packing contacts the lower gauge fitting.
DO NOT allow the glass to remain in contact with any metal!
6.
Carefully slide upper glass packing up as far as possible.
7.
Hand tighten both glass packing nuts, then tighten 1/2 turn more
by wrench.Tighten only enough to prevent leakage. DO NOT OVER
TIGHTEN! If any leakage should occur, tighten lightly, a quarter
turn at a time, checking for leakage after each turn.
IMPORTANT NOTE:
Read all warnings and instructions before
performing installation or maintenance.
!
WARNING
Vessel Wall
Gauge Glass
Glass Packing
Nut
Glass Packing
Top Gauge
Fitting
Guard Rod
Friction Washer
(or Packing Gland)
Bottom
Gauge
Fitting
Drain Valve
A
B