Post-Installation Configuration & Checkout
GNS 480 (CNX80) Installation Manual
560-0982-01 Rev L
3-1
3
Post Installation Configuration & Checkout Procedures
Once the GNS 480 unit has been installed, configure the unit for the particular installation and then
complete the checkout procedures herein to verify proper operation. The steps that are not applicable to a
particular installation may be skipped. A checkout log sheet is included in Table 3-7 on page 3-45, to be
filled out during the checkout procedure. The completed checkout log sheet should be maintained with
the aircraft permanent records.
3.1
Mounting and Wiring Check
Verify that all cables are properly secured and shields are connected as the install drawings indicate.
Installation may require that you check the movement of the aircraft controls to verify that there is no
interference.