Starting
Procedure for
controller as shown
Step
Action
-
At least 10 minutes before starting, the main supply to the dryer must be switched on to
initialize the
controller and flow switch.
-
Close the dryer by-pass valve, if installed.
-
Press start button (14).
-
Open the dryer air inlet valve (customer's installation).
-
Approx. 5 minutes later, open the dryer air outlet valve (customer's installation).
-
Approx. 10 minutes later, the nominal dew-point will be reached.
5.4
During operation
Description for
controller as shown