This section is an overview of the steps required to commission a link in the field.
Phase 1: Pre-installation
1.
Confirm path planning.
Page 19
2.
Ensure that the site preparation is complete:
Power
requirements
Tower
requirements
Environmental considerations, for example, temperature control
Rack
space
Page 22
3.
Confirm the interface card configuration.
Phase 2: Installing the terminals
1.
Before installing the terminal into the rack, check that all the required
interface cards are fitted.
Position and mount the terminal in the rack.
Page 29
2.
Connect earthing to the terminal.
Page 24
3.
Confirm that the:
Antenna is mounted and visually aligned.
Feeder cable is connected to the antenna.
Feeder connections are tightened to recommended level.
Tower earthing is complete.
4.
Install lightning protection.
Page 24
5.
Connect the coaxial jumper cable between the lightning protection and the
terminal duplexer.
6.
Connect the power supply to the terminal and apply power.
Page 31