Objet Alaris Preparation And Installation Manual

Summary of Alaris

  • Page 1

    Objet proprietary information alaris 3‐d printer site preparation guide doc‐04002 rev. C march 2010 objet geometries ltd..

  • Page 2: Copyright

    Alaris site preparation guide objet confidential and proprietary information doc-04002 2 rev. C copyright copyright © 2010 by objet geometries ltd. All rights reserved. This documentation contains proprietary information of objet geometries ltd. This information is supplied solely to assist objet‐au...

  • Page 3: Contents

    Alaris site preparation guide objet confidential and proprietary information doc-04002 3 rev. C contents 1 introduction 1.1 about this guide ...................................................................................... 5 1.2 installation and training............................................

  • Page 4

    Alaris site preparation guide objet confidential and proprietary information doc-04002 4 rev. C 5.6 heat dissipation ..................................................................................... 16 5.7 air conditioning ............................................................................

  • Page 5: 1  Introduction

    Alaris site preparation guide objet confidential and proprietary information doc-04002 5 rev. C 1 introduction 1.1 about this guide this document provides site preparation information and requirements for alaris 3‐d printing systems to ensure proper system installation and operation. The customer is...

  • Page 6: 2  Physical Description

    Alaris site preparation guide objet confidential and proprietary information doc-04002 6 rev. C 2 physical description 2.1 configuration the alaris 3‐d printing system consists of the following main components: • the alaris 3‐d printer • the alaris computer (built into the printer) • a printer‐serve...

  • Page 7: 2.3  Start-Up Kit

    Alaris site preparation guide objet confidential and proprietary information doc-04002 7 rev. C 2.3 start-up kit the alaris printer comes equipped with a start‐up kit, which includes tools and accessories. These tools and accessories may be required during the installation and are available for use ...

  • Page 8: 3  Shipment and Delivery

    Alaris site preparation guide objet confidential and proprietary information doc-04002 8 rev. C 3 shipment and delivery 3.1 shipping information and responsibility the objet distributor will arrange shipment to the customer’s facilities, as indicated in the “ship to” part of the invoice. It is the c...

  • Page 9: 3.4  Unloading Space

    Alaris site preparation guide objet confidential and proprietary information doc-04002 9 rev. C 3.4 unloading space in order to select the correct type of truck to deliver the printer, the presence or absence of a loading dock at the customer site must be identified. Check the route from the unloadi...

  • Page 10: 4  Site Requirements

    Alaris site preparation guide objet confidential and proprietary information doc-04002 10 rev. C 4 site requirements the following factors should be considered when choosing a suitable location for the alaris printer and server workstation: • isolation from sources of vibration such as generators an...

  • Page 11

    Alaris site preparation guide objet confidential and proprietary information doc-04002 11 rev. C figure 4–1 is a sample floor plan, showing the space required for the system units and the minimum recommended service area for the printer. Figure 4–1 floor plan (minimum maintenance distances shown) if...

  • Page 12: 4.4  Doors and Hallways

    Alaris site preparation guide objet confidential and proprietary information doc-04002 12 rev. C 4.2 table height & strength the height of the table should be 62–72 cm (2 feet to 2 feet, 4 inches). This establishes a working height of 100–110 cm (2 feet, 3 inches to 2 feet, 7 inches). The stand/tabl...

  • Page 13: 5  Facility Requirements

    Alaris site preparation guide objet confidential and proprietary information doc-04002 13 rev. C 5 facility requirements 5.1 electrical power requirements 5.1.1 power requirements alaris printers have the following power rating: a type c circuit breaker with the following specification is recommende...

  • Page 14: 5.3  Communication Lines

    Alaris site preparation guide objet confidential and proprietary information doc-04002 14 rev. C the following wall outlets are required: • one wall outlet behind the printer (for the printer) this should be connected directly to the main electrical panel. • three wall outlets close to the printer (...

  • Page 15: 5.4  Server Workstation

    Alaris site preparation guide objet confidential and proprietary information doc-04002 15 rev. C 5.4 server workstation the customer must provide a computer for the server workstation, with the following minimum requirements: the server workstation must have a user with administrator privileges. No ...

  • Page 16: 5.5  Network

    Alaris site preparation guide objet confidential and proprietary information doc-04002 16 rev. C 5.5 network a network connection is required near the server workstation. Figure 5–1 network connection 5.6 heat dissipation table 7 describes the heat dissipation of the system units. 5.7 air conditioni...

  • Page 17

    Alaris site preparation guide objet confidential and proprietary information doc-04002 17 rev. C 5.7.2 humidity the relative humidity in the room containing the alaris system should be 30%–70% non‐condensing. The room requires constant refreshing of the humid air by appropriate ventilation units (re...

  • Page 18: 5.11  Fire Control

    Alaris site preparation guide objet confidential and proprietary information doc-04002 18 rev. C 5.10 storage of printing materials 5.10.1 storage and transport conditions store containers of model and support materials, indoors, in a dry area with adequate ventilation and with the temperature kept ...

  • Page 19: 6 Site

    Alaris site preparation guide objet confidential and proprietary information doc-04002 19 rev. C 6 site preparation checklist dear customer, thank you for reading this site preparation guide. Please fill in the customer informa- tion and table below and fax it to your local objet contact person (aft...

  • Page 20

    Alaris site preparation guide objet confidential and proprietary information doc-04002 20 rev. C full name: ______________________________________ customer signature: ______________________date: ________________________ item and reference completed (according to spec.) notes yes no floor area and st...