Wacker Neuson LTV6K Operator's manual - Ltv
wc_tx004431gb_FM10.fm
63
LTV
Operation
Continued from the previous page.
Operating the
lights
Perform the procedure below to operate the lights.
1. Turn on the main circuit breaker (a).
2. Turn on individual circuit breakers (c) one at a time.
Notes
■ Metal halide floodlights require a warm-up time of 5–15 minutes before they
reach full brightness.
■ After turning the lights off, a cool-down time of 10 minutes is necessary before
they can be turned on again.
Stopping the
machine
NOTICE: Turn off the lights before stopping the engine. Failure to do so will
damage the electrical system.
Perform the procedure below to stop the machine.
1. Disconnect all loads from the machine.
2. Turn the circuit breakers (a) off.
3. Rotate the key (e) to the OFF position.
wc_gr013751
a
b
d
c
e
g
f
8K