(1) Cabinet assembly
2,3
1
z
Package contents
No
Name
Specification
Qty.
1
Cabinet assembly
1
2
Service key
Taped on the cabinet.
2
3
Cash box key
Taped on the cabinet.
2
(2), (3) Pillar assembly
z
Package contents
No
Name
Specification
Qty.
1
Pillar assembly
4 (2 per package)
(4) Control panel assembly
z
Package contents
No
Name
Specification
Qty.
1
Control panel assembly
yellow, blue, red, green
4 (one for each