Gas analyzer start-up
Topic Page
Checking and approving for use ......................................................................153
Connecting the supply voltage ........................................................................ 156
Recognizing the operating status ................................................................... 156
Connecting the PC to the junction box ........................................................... 157
Connecting to the instrument software ........................................................ 158
Menu structure of the instrument software ................................................. 159
Main menu ........................................................................................................... 160
System time menu .............................................................................................. 161
Fine alignment of the purging flanges ........................................................... 162
Alignment menu.................................................................................................. 164
Installation procedure ....................................................................................... 165
Installation – Process parameters menu ....................................................... 166
Installation – Installation flanges menu ......................................................... 168
Installation – Ambient conditions menu ........................................................ 170
Installation – External inputs menu ................................................................. 171
Installation – Channels menu ............................................................................ 172
Installation – Analog and digital outputs menu ............................................ 173
Installation – Network settings menu ............................................................. 175
Installation – Save settings menu .................................................................... 176
Checking and approving for use
Ensure that all pre-startup conditions are met.
Proceed in accordance with the following checklists:
Test object
Requirement
Transmitter unit,
receiver unit,
junction box
The environmental conditions are consistent with the
following information on the name plate:
Zone
Explosion group
Temperature class
Ambient temperature
Test object
Requirement
Junction box
The junction box meets the following requirements:
The junction box is not damaged
The junction box has been installed in a stable manner
The junction box is closed so that no dust can penetrate
All of the fixing screws on the housing cover are pre-
sent and securely tightened.
Performing a final
check of the analyzer
Checking the
environmental
conditions
Checking the
mechanical system