ABB LS4000 Operating Instructions Manual - page 73
LS4000, LS4060 DIODE LASER ANALYZERS | OI/LS4000/O2-EN REV. A
73
Option: Installing the validation cell
Topic Page
Providing an overview ......................................................................................... 73
Installing the validation cell ................................................................................ 74
Providing an overview
If …
then …
the process must be validated
due to the application
a validation cell must be installed. This is
included in the scope of delivery, depend-
ing on the application.
no validation cell is installed
validations can only be performed inde-
pendently of the process on the separate
calibration set.
No.
Meaning
1
Transmitter unit
2
Validation cell
3
Test gas supply and discharge
4
Purging flange
5
Process
6
Purging flange
7
Receiver unit
The purging flanges have a ¼ inch Swagelok® connection for pipes with an
8 mm outside diameter.
The validation cell is to be installed on the side of the transmitter unit.
Under what
circumstances is a
validation cell
required?
Providing an
overview