Vent-Axia Sentinel Kinetic B Left Installation & Commissioning Manual - page 13
Installation
Sentinel Kinetic MVHR Installation & Commissioning
13
Installation
NOTE: we advise installers to fix all mains and sensor wiring along with any internal accessories prior
to fixing the MVHR unit in position, leaving approximately 500 mm tails to allow for internal routing.
Before Installation of the Unit
Inspect the Unit
When taking delivery of the unit, check the items delivered against the enclosed delivery note. Inspect the unit
for damage in transit. If in doubt, contact Customer Services. Each box contains a Kinetic HR unit and an
accessory pack containing wall brackets, condensate drain link pipe, pipe clips, fixings and product
documentation.
Lift and Move the Unit Safely
On page 7 check the weight of the unit that you are installing. Always use appropriate lifting techniques and
appliances when moving heavy equipment.
Check Site Requirements and Safety Notices
Check that the physical and environmental conditions for the site meet, or exceed, the requirements detailed in
the Technical Specification on page 7.
Read and observe the safety notices listed in Warnings and Safety Information on page 2.
Unit Installation
The wall should have sufficient strength to support the unit.
Take into consideration the position of the electrical services and the condensate drain.
Ensure there is adequate access for installation, operation and maintenance.
It is recommended that a local disconnection mains and sensor terminal box is installed within 1m of the unit to
facilitate future maintenance.
The unit MUST always be mounted vertically with ducting exiting vertically or horizontally. Do not use this unit
as a support for any other equipment.
If installing in a cold void for optimum performance insulate the unit