Horizontal Discharge Condensate Installation
To install the condensate horizontal discharge:
1. For horizontal discharge, remove the front
cover and locate the condensate stub at the
front of the unit.
2. Remove the Black Cap from end of
condensate stub at the front of the unit.
3. On the Kinetic drill a diameter 32 mm hole
where shown, right.
On the Kinetic Plus drill a diameter 32 mm
hole using the indent provided in the
moulding as a guide.
The hole is a clearance hole for a diameter
22 mm pipe and so may vary a little from
this guidance.
60 mm
21 mm