Vent-Axia Sentinel Kinetic B Left Installation & Commissioning Manual - page 20
Installation
Sentinel Kinetic MVHR Installation & Commissioning
20
Floor Mounting Sentinel Kinetic Plus and Kinetic High Flow
1. Remove the front and rear covers.
2. Ensure that a secure, firm, flat and level surface is
provided to place the Kinetic Plus unit on.
3. Screw down through the white plastic base plate of the
unit to a board which may then be screwed to joists,
flooring or equivalent.
4. The unit should now be physically installed in its
intended operating location.
Attach the ducting:
1. Always use a short piece of flexible duct 100-150 mm
long, extended to its full length when connecting to
ductwork.
2. Securely connect this ducting to the spigots using
worm-drive clips or cable ties.
3. Insulate any ducting passing through an unheated
space to prevent any heat losses and surface
condensation.