4RF Aprisa SR+ User Manual - Getting Started
Getting Started | 13
Aprisa SR+ User Manual 1.5.3
1.
Getting Started
This section is an overview of the steps required to commission an Aprisa SR+ radio network in the field:
Phase 1: Pre-installation
1.
Confirm path planning.
Page 52
2.
Ensure that the site preparation is complete:
Power requirements
Tower requirements
Environmental considerations, for example, temperature control
Mounting space
Page 55
Phase 2: Installing the radios
1.
Mount the radio.
Page 58
2.
Connect earthing to the radio.
Page 57
3.
Confirm that the:
Antenna is mounted and visually aligned
Feeder cable is connected to the antenna
Feeder connections are tightened to recommended level
Tower earthing is complete
4.
Install lightning protection.
Page 57
5.
Connect the coaxial jumper cable between the lightning protection and the
radio antenna port.
Page 62
6.
Connect the power to the radio.
Page 63