4RF Aprisa SR+ User Manual - 1. Getting Started
Getting Started | 11
Aprisa SR User Manual
1. Getting Started
This section is an overview of the steps required to commission an Aprisa SR radio network in the field:
Phase 1: Pre-installation
1.
Confirm path planning.
Page 44
2.
Ensure that the site preparation is complete:
Power requirements.
Tower requirements.
Environmental considerations, for example, temperature control.
Mounting space.
Page 47
Phase 2: Installing the radios
1.
Mount the radio.
Page 50
2.
Connect earthing to the radio.
Page 49
3.
Confirm that the:
Antenna is mounted and visually aligned.
Feeder cable is connected to the antenna.
Feeder connections are tightened to recommended level.
Tower earthing is complete.
4.
Install lightning protection.
Page 49
5.
Connect the coaxial jumper cable between the lightning protection and the
radio antenna port.
Page 53
6.
Connect the power to the radio.
Page 54