IN5TALLATION OF THE ELEVATORS
.....
The elevators are installed and rigged prior to the canard being
mated to the fuselage. As a result, after mating only C513 needs to be
hooked up for a functioning pitch control system.
.....
The procedures detailed here are similar in scope to what you have
already accomplished in mounting the ailerons on the main wing, except
that the elevators have a center pivot on each side.
.....
Begin by jigging the canard vertically, with the leading edge at
the table.
.....
Take a piece of QC5Ml and make two 1.8" 1ength pieces to use as
elevator reducers. A saw cut and perhaps some light sanding will be
necessary to make them fit snugly and flush with the inboard ends of the
two elevators.
.....
Find the phenolic bearings C515 (2) and C514 (1). Dull the phenolic
completely with sandpaper except inside the reamed 5/8" diameter holes.
Be sure that the other 1/2" diameter holes have been drill ed out. These
are non-critical on diameter, but must be there to assist bonding of the
phenolic to the structure. They are NOT lightening holes.
.....
Find Q2C5A8. Make C520 from 0.625" 0.0. x 0.065" wall 4130 steel
tubing. The length of C520 should be about 5" longer than 1/2 the width
of the fuselage where the elevator matches up to the fuselage. The piece
is made long initially, and then trimmed back as needed.
.....
The right and left elevators are nearly mirror images of one
another. Each elevator has an outboard hinge C519, a midspan hinge C517,
and a inboard hinge C515. Q2C5A8 slips into the elevator reducer at the
elevator end, and over a AN271-B8 (or M52071-B8) universal joint near
BLOO. On the right side, C520 slips into the elevator reducer at the
elevator end, and through C514 and then over the same AN271-B8 (or
M520271-B8) universal joint near BLOO. Clear, heh?
.....
The following procedure was developed to help you get the elevators
mounted without binding, with the proper clearances, and with the
ability to get them off again: