not interfere with the elevator movement, or bond
the elevator to the shear web. If you previously
removed the top and bottom canard skin where the
slot was ground out, be sure to laminate 2 BID top
and bottom once the laminations have cured. . The
above procedures are used with both elevators.
8.
Once the laminations and installation have cured,
you are ready to drill in the elevator assemblies.
Find your elevator rigging template! reassemble
every thing, and set the elevators at 0 degrees.
Also, verify that each elevator is pushed outboard
against CS19. Verify that both Q2CSA8 and CS20
overlap into the elevator reducers a minimum of
1.8", and that both are pushed up tight onto the
universal joint. Now drill in very carefully the
four bolts that fasten Q2CSA8, CS20, universal
joint, and CS16/ elevator reducer together. BE
CAREFUL! Don't let the holes elongate; use a small
drill and work up in size. Also, be absolutely
sure that each elevator is at the same angle (i.e.
no asymmetry) and that full elevator deflection is
available without any interference any where in
the system.
9.
Finally, make the elevator spacers, which have a
nominal length of 1.0" each. The actual length
should be sized to allow the elevator to have a
lateral freeplay (i.e. inboard to outboard) of
about 0.05". Assemble each elevator, and again
check for binding, misalignment, or excessive
freeplay.