Scheduling an NQA Test Group
With this configuration, you can set the start time and test duration for a test group to perform NQA tests.
The start time can take a specific value or can be now, which indicates that a test is started immediately;
the test duration can take a specific value or can be forever, which indicates that a test will not stop until
you use the undo nqa schedule command to stop the test.
A test group performs tests when the system time is between the start time and the end time (the start
time plus test duration). If the system time is behind the start time when you execute the nqa schedule
command, a test is started when the system time reaches the start time; if the system time is between
the start time and the end time, a test is started at once; if the system time is ahead of the end time, no
test is started. You can use the display clock command to view the current system time.
Configuration prerequisites
Before scheduling an NQA test group, make sure:
z
Required test parameters corresponding to a test type have been configured;
z
For the test which needs the cooperation with the NQA server, configuration on the NQA server
has been completed.
Scheduling an NQA test group
Follow these steps to schedule an NQA test group:
To do…
Use the command…
Remarks
Enter system view
system-view
—
Schedule an NQA test group
nqa schedule admin-name operation-tag
start-time {hh:mm:ss[yyyy/mm/dd ]|
now } lifetime {lifetime| forever }
Required
Configure the maximum
number of the tests that the
NQA client can simultaneously
perform
nqa agent max-concurrent number
Optional
2 by default.
z
After an NQA test group is scheduled, you cannot enter the test group view or test type view.
z
A started test group or a test group that has completed tests will not be influenced by the system
time change; only a test group that is waiting to perform tests will be influenced by the system time
change.